Boeing Profit Soars Despite Dreamliner Issue

Written By Unknown on Kamis, 25 April 2013 | 11.46

Boeing 787 Dreamliner Timeline

Updated: 12:07pm UK, Monday 22 April 2013

The turbulent history of the Boeing 787 Dreamliner:

Apr 22, 2013: The batteries in five All Nippon Airways Dreamliners and two Japan Airlines jets are replaced

Apr 19, 2013: The Federal Aviation Administration approves Boeing's battery modification plans

Apr 3, 2013: Company says it has completed more than half of its battery tests

Mar 25, 2013: Boeing says its first test flight with the new lithium-ion battery went according to plan.

Mar 15, 2013: Boeing unveils modifications to its 787 batteries, saying the Dreamliner is "absolutely safe"

Mar 12, 2013:  FAA approves Boeing's certification plan for a new battery system for the aircraft

Mar 7, 2013: US National Transportation Safety Board says it has failed to identify the cause of the Jan 7 fire

Feb 28, 2013: Boeing says it has found a "permanent" solution to fix problems with Dreamliner batteries

Feb 25, 2013: All Nippon Air (ANA) confirms all of its fleet will remain grounded until the end of May

Feb 8, 2013: Boeing confirms it has sent letters to airlines expecting imminent deliveries of possible delays

Feb 7, 2013: US Federal Aviation Administration (FAA) allows limited test flight of the grounded Dreamliner

Feb 5, 2013: Japanese official reveal CT scans of failed batteries does not reveal fire cause

Feb 4, 2013: Boeing requests FAA approval for test flights of grounded model

Jan 30, 2013: Amid revenue loss forecasts of $500m to $5bn, Boeing CEO addresses investors and downplays impact

Jan 28, 2013: Investigators widen battery examination to sub-contractors of lithium ion battery maker GS Yuasa

Jan 21, 2013: Safety officials start probe of lithium ion battery maker GS Yuasa

Jan 19, 2013: Boeing says it is stopping deliveries of the Dreamliner to airlines

Jan 18, 2013: FAA officials arrive in Japan to examine a 787 and its melted battery pack after an ANA emergency landing two days earlier

Jan 17, 2013: The European Aviation Safety Agency,  FAA and Qatar Airways ground Dreamliners under their regulatory control

Jan 16, 2013: Japan Air Lines Co Ltd (JAL) follows suit and suspends Dreamliner flights from Japan over safety concerns

Jan 16, 2013: ANA grounds all 17 of its 787s after four of its aircraft suffer problems

Jan 16, 2013: ANA 787 Dreamliner makes emergency landing in Takamatsu, Japan, after smoke appears in cabin

Jan 11, 2013: The Federal Aviation Administration (FAA) announces a review of the 787 design and systems

Jan 11, 2013: ANA discovers engine oil leak after a domestic flight lands at Miyazaki

Jan 11, 2013: A separate ANA flight to Matsuyama reported a crack appearing in the pilot's window

Jan 9, 2013: ANA cancels a Boeing 787 Dreamliner flight due to a brake problem

Jan 8, 2013: Japan Air Lines (JAL) grounds a jet at Boston Logan International Airport after a 787 leaks 150 litres of fuel

Jan 7, 2013: A fire erupts in a battery pack in another JAL Dreamliner at Boston

Dec 13, 2012: Qatar Airways grounds one of its Dreamliners because of a faulty generator

Dec 5, 2012: The FAA orders inspections of all 787 Dreamliners in service in the US

Dec 4, 2012: A United Airlines 787 is forced to make an emergency landing in New Orleans after a generator fails

July 23, 2012: ANA grounds five Dreamliners due to an engine component issue

Feb 22, 2012: Boeing says around 55 Dreamliners may be affected by a flaw in the fuselage

Oct 26, 2011: The Dreamliner makes its maiden flight with paying passengers on board an ANA jet

Sep 26, 2011: Boeing delivers its first 787 Dreamliner to Japan's ANA, three years late

Jun 23, 2010: Boeing postpones the first flight of the Dreamliner because of a structural flaw

Dec 15, 2009: The passenger jet 787 Dreamliner takes off on its maiden test flight

Apr 9, 2008: Boeing says there will be a revised plan for the first 787 flight and initial deliveries

Dec 11, 2008: Boeing announces further delays due to strike action by machinists Sept-Nov

Oct 19, 2007: Boeing says there will be a six-month delay to deliveries due to assembly issues

Jul 8, 2007: The first assembled 787 goes on display to media, employees and customers

Jul 18, 2006: Boeing says it is making "solid progress" on the 787 Dreamliner programme

Jan 28, 2005: Boeing gives its new commercial airplane an official model designation number - 787

Jan 29, 2003: Boeing announces the launch of a new aircraft called the 7E7


Anda sedang membaca artikel tentang

Boeing Profit Soars Despite Dreamliner Issue

Dengan url

http://kaumkusaman.blogspot.com/2013/04/boeing-profit-soars-despite-dreamliner.html

Anda boleh menyebar luaskannya atau mengcopy paste-nya

Boeing Profit Soars Despite Dreamliner Issue

namun jangan lupa untuk meletakkan link

Boeing Profit Soars Despite Dreamliner Issue

sebagai sumbernya

0 komentar:

Posting Komentar

techieblogger.com Techie Blogger Techie Blogger